Project scope is vital for successful project execution and involves understanding all of a project's key elements. Here's what you need to know to achieve your project goals. Credit: Alvaro Reyes / Unsplash Clearly defining your project’s scope helps to effectively manage stakeholder expectations and ensures that all of the project’s elements are aligned with the objectives — increasing the chances of success. Here’s what you need to know about defining project scope. Project scope definition Project scope is a detailed outline of all aspects of a project, including all related activities, resources, timelines, and deliverables, as well as the project’s boundaries. A project scope also outlines key stakeholders, processes, assumptions, and constraints, as well as what the project is about, what is included, and what isn’t. All of this essential information is documented in a scope statement. The project scope statement The project scope statement is a key document that provides all stakeholders with a clear understanding of why the project was initiated and defines its key goals. Most project scope statements will include these elements. A project statement of work (SoW), which is a detailed breakdown of all work to be performed by a project team and any important elements that may impact the outcomeConstraints that might limit or negatively impact the outcome of the project, including resources, procurement issues, timing, or lack of informationScope exclusions, which can be anything that will not be part of the project or its deliverablesMilestones that provide the exact date that something will be delivered or completedThe final deliverables that will be provided to the customer at the end of the project — for example, a report, a software feature, any process insights or analysis, or any product or service that a customer needsAcceptance criteria that spell out exactly how success will be measuredFinal approval whereby the customer will sign-off on the scope statement confirming that all parameters have been included and the document is complete and accurate Key steps for defining your project scope Properly defining the scope of a project is the key to successfully managing your project. Here are the steps you can follow to define your project scope. Work with key stakeholders to define and create a scope statement by identifying what is within scope, and out of scope. Collaborating with stakeholders helps to ensure essential things do not fall through the cracks.Identify, document, and communicate assumptions. Assumptions are those elements that relate to the project that are assumed to be true for the duration of the project. Assumptions are necessary to provide an estimate of the cost and schedule to deliver the project’s scope during the planning phase of a project.Gain buy-in for the scope statement with the stakeholders who are most impacted to ensure that everyone is on the same page. Project scope example Let’s say you are a project manager defining the scope for a content marketing project. A very simple project scope statement might include the following. Introduction. This content marketing project is being undertaken for XYZ company for the purpose of creating an article to be posted on their site to create brand awareness.Project Scope. This project will include research, content strategy, writing the article, and publishing it on XYZ’s website under the XYZ blog. It will also include sharing the article on social media for the month of April 2020. All activities will be conducted by Joe Smith of ABC company.Project Deliverables. Project deliverables will include one well-researched written article of up to 1,000 words to be delivered by email to Jane@XYZ.com no later than ___ date. Project Acceptance Criteria. Jane at XYZ company will review and approve the final article version before publishing.Project Exclusions. This project will not include payment to external vendors for research or outsourced services.Project Constraints. Constraints may include communication delays, changes in scope, or technical difficulties. Once the project scope statement is complete and approved, and a project is underway, the project scope will need to be carefully managed to avoid scope creep. What is scope creep? Scope creep refers to a scenario whereby changes occur after the project has been started and the changes are not defined or anticipated within the scope statement. When scope creep occurs, it can negatively impact the project timeline, deliverable quality, resources, budget, and other aspects. Managing the scope of your project can help avoid unwelcome surprises. Project scope management In addition to the ongoing review and monitoring of project activities, there are steps that should be undertaken to manage the scope of the project to avoid scope creep. Identify whether there are any changes to the requirements for your project. This is a vital step since these changes directly affect the project goals and all related activities.Identify how the changes will impact the project. Before you can make adjustments to the scope of the project, you need to understand where and how changes impact the outcome.Gain approval for changes before proceeding with a change in activities or direction.Implement the approved changes in a timely manner to reduce delays and risks. For more on managing project scope, see “7 tips for containing project scope.” Project scope template [Project Title] – Project Scope Introduction. The Introduction provides a high-level overview of the project.Project Scope. State the scope of the project. This should include what the project does and does not include. This will help to clarify what is included in the project and help to avoid any confusion from project team members and stakeholders.Project Deliverables. State the planned deliverables for the project. Project Acceptance Criteria. Define the acceptance criteria. What objectives will be met, and how will success be measured?Project Exclusions. What is not included in the scope of this project.Project Constraints. Provide any constraints on the project, hard dates, staff or equipment limitations, financial or budget constraints, or any technical limitations. Developing a solid understanding of a project’s purpose and clearly defining, documenting, and managing your project scope, you can ensure that you are well-positioned to deliver a successful project without having to deal with scope creep. More on project management: Project management guide: Tips, strategies, best practicesTop 20 project management methodologiesWhat is a project manager? The lead role for project successTop 15 project management certifications7 must-have project management skills Related content feature The startup CIO’s guide to formalizing IT for liquidity events CIO turned VC Brian Hoyt draws on his experience prepping companies for IPO and other liquidity events, including his own, to outline a playbook for crossing the start-up to scale-up chasm. By Michael Bertha and Duke Dyksterhouse 01 Mar 2024 9 mins CIO Startups IT Strategy feature 15 worthwhile conferences for women in tech For women seeking to connect and advance their IT careers, or those who support diversity and inclusion in technology fields, here are 15 conferences you won’t want to miss. By Sarah K. White 01 Mar 2024 11 mins Women in IT Diversity and Inclusion IT Skills brandpost Sponsored by Avanade By enabling “ask and expert” capabilities, generative AI like Microsoft Copilot will transform manufacturing By CIO Contributor 29 Feb 2024 4 mins Generative AI Innovation feature Captive centers are back. Is DIY offshoring right for you? Fully-owned global IT service centers picked up steam in 2023, but going the captive route requires clear-eyed consideration of benefits and risks, as well as desired business outcomes. By Stephanie Overby 29 Feb 2024 10 mins Offshoring IT Strategy Outsourcing PODCASTS VIDEOS RESOURCES EVENTS SUBSCRIBE TO OUR NEWSLETTER From our editors straight to your inbox Get started by entering your email address below. Please enter a valid email address Subscribe